The team continues to make good progress at Seaward’s new development in Southbourne with the road construction well under way. Tarmac is due to be laid on 4th July.
Last week the sub-structure blockwork, internal drainage and services for Plots 1, 2, 3, 4, 5 and 6 were completed ready for the beam and block floor this week.